COMMONWEALTH OF VIRGINIA DEPARTMENT OF MINES, MINERALS AND ENERGY

DIVISION OF MINED LAND RECLAMATION P.O. DRAWER 900, BIG STONE GAP, VA 24219

TELEPHONE: (276) 523-8198

ABANDONED MINE LAND INSPECTION

DMLR-AML-130S Printed: 02/04/20 5/06 Page 1 of 1

HNM0009019

PROJECT NAME PROJECT NO. GRANT YEAR REPORT NUMBER

Golden Pond Gob Removal 18302 2018 HNM0009019

CONTRACT INFORMATION

CONTRACT NUMBER EXPIRATION DATE PERCENT OF CONTRACT COMPLETED

C196013 03/31/21 15

CONTRACTOR NAME ENGINEER NAME

Russell County Reclamation, LLC SCOTTY COX

SITE CONTACT PERSON: Kevin Large

INSPECTION DATE ARRIVAL DEPARTURE GROUND CONDITION

01/15/20 01/23/20

03:30 PM 03:00 PM

04:30 PM 04:00 PM

WET WET

INSPECTION BY ATTACHMENTS

MCDONALD-TAYLOR, H.

COMMENTS

Material removal continued throughout the month. Excavation has moved beyond the building site. At the time of the inspection, excavators were working both sides of the structure.

COMMONWEALTH OF VIRGINIA HNM0009019

DEPARTMENT OF MINES, MINERALS AND ENERGY Dh DIVISION OF MINED LAND RECLAMATION

P.O. DRAWER 900, BIG STONE GAP, VA 24219 Virginia Depay TELEPHONE: (276) 523-8198

Mines Minerals and Energy

ABANDONED MINE LAND INSPECTION

PROJECT NAME, PROJECT NO. GRANT YEAR | REPORT NUMBER

Golden Pond Gob Removal 18302 2018 HNM0009019

CONTRACT INFORMATION

CONTRACT NUMBER EXPIRATION DATE, PERCENT OF CONTRACT COMPLETED €196013 03/31/21 15 CONTRACTOR NAME ENGINEER NAME, Russell County Reclamation, LLC SCOTTY COX SITE CONTACT PERSON: Kevin Large INSPECTION DATE ARRIVAL DEPARTURE. GROUND CONDITION 01/15/20 03:30 PM 04:30 PM WET 01/23/20 03:00 PM 04:00 PM WET INSPECTION BY ATTACHMENTS

MCDONALD-TAYLOR, H.

[ COMMENTS

Material removal continued throughout the month. Excavation has moved beyond the building site. At the time of the inspection, excavators were working both sides of the structure.

DMLR-AML-130S Printed: 02/04/20 5/06 Page 1 of 1