COMMONWEALTH OF VIRGINIA DEPARTMENT OF MINES, MINERALS AND ENERGY

DIVISION OF MINED LAND RECLAMATION P.O. DRAWER 900, BIG STONE GAP, VA 24219

TELEPHONE: (276) 523-8198

ABANDONED MINE LAND INSPECTION

DMLR-AML-130S Printed: 01/07/19 5/06 Page 1 of 1

HNM0008430

PROJECT NAME PROJECT NO. GRANT YEAR REPORT NUMBER

Golden Pond Gob Removal 18302 2018 HNM0008430

CONTRACT INFORMATION

CONTRACT NUMBER EXPIRATION DATE PERCENT OF CONTRACT COMPLETED

C196013 03/31/21 0

CONTRACTOR NAME ENGINEER NAME

Russell County Reclamation, LLC SCOTTY COX

SITE CONTACT PERSON: Kevin Large

INSPECTION DATE ARRIVAL DEPARTURE GROUND CONDITION

12/12/18 10:00 AM 11:15 AM FROZEN

INSPECTION BY ATTACHMENTS

MCDONALD-TAYLOR, H.

COMMENTS

A meeting was held on site on 12-12-18 with Heather McDonald-Taylor, Lesa Baker and Clara Harris from DMME and William Wampler, Kevin Large and Dave Powers with the company. The site was reviewed and future plans discussed.
Work has not yet begun on the site. Large scale material removal cannot begin until the material within the structure is partially dried. Pumping cannot commence until the ponds on permit 1302253 are approved to receive the drainage.
That is addressed in application 1010465. That application is likely to be approved soon. Pumping will commence as soon as the application is approved. Large scale gob removal will likely not commence until spring.

COMMONWEALTH OF VIRGINIA HNM0008430

DEPARTMENT OF MINES, MINERALS AND ENERGY Dh DIVISION OF MINED LAND RECLAMATION

P.O. DRAWER 900, BIG STONE GAP, VA 24219 Virginia Depay TELEPHONE: (276) 523-8198

Mines Minerals and Energy ABANDONED MINE LAND INSPECTION

PROJECT NAME, PROJECT NO. GRANT YEAR | REPORT NUMBER

Golden Pond Gob Removal 48302 2018 HNM0008430

CONTRACT INFORMATION

CONTRACT NUMBER EXPIRATION DATE, PERCENT OF CONTRACT COMPLETED

C196013 03/31/21 0 CONTRACTOR NAME ENGINEER NAME,

Russell County Reclamation, LLC SCOTTY COX

SITE CONTACT PERSON: Kevin Large

INSPECTION DATE, ARRIVAL DEPARTURE. GROUND CONDITION 42/12/18 10:00 AM 14:15 AM FROZEN INSPECTION BY ATTACHMENTS

MCDONALD-TAYLOR, H.

[ COMMENTS:

A meeting was held on site on 12-12-16 with Heather McDonald-Taylor, Lesa Baker and Clara Harris from DMME and William Wampler, Kevin Large and Dave Powers with the company. The site was reviewed and future plans discussed. Work has not yet begun on the site. Large scale material removal cannot begin until the material within the structure is partially dried. Pumping cannot commence until the ponds on permit 1302253 are approved to receive the drainage. That is addressed in application 1010465. That application is likely to be approved soon. Pumping will commence as soon as the application is approved. Large scale gob removal will ikely not commence until spring

DMLR-AML-130S Printed: 01/07/19 5/06 Page 1 of 1