COMMONWEALTH OF VIRGINIA
|
||
DEPARTMENT OF MINES, MINERALS AND ENERGY
|
||
|
||
DIVISION OF MINED LAND RECLAMATION
|
||
P.O. DRAWER 900, BIG STONE GAP, VA 24219
|
||
|
||
TELEPHONE: (276) 523-8198
|
||
|
||
|
||
ABANDONED MINE LAND INSPECTION
|
||
|
||
|
||
DMLR-AML-130S Printed: 04/06/21
|
||
5/06 Page 1 of 1
|
||
|
||
|
||
HNM0009561
|
||
|
||
|
||
|
||
PROJECT NAME PROJECT NO. GRANT YEAR REPORT NUMBER
|
||
|
||
Project Reclaim Phase II 91806 2018 HNM0009561
|
||
|
||
|
||
|
||
CONTRACT INFORMATION
|
||
|
||
CONTRACT NUMBER EXPIRATION DATE PERCENT OF CONTRACT COMPLETED
|
||
|
||
20
|
||
|
||
CONTRACTOR NAME ENGINEER NAME
|
||
|
||
|
||
|
||
SITE CONTACT PERSON: Kevin Large
|
||
|
||
|
||
|
||
INSPECTION DATE ARRIVAL DEPARTURE GROUND CONDITION
|
||
|
||
02/03/21
|
||
02/23/21
|
||
|
||
03:00 PM
|
||
03:30 PM
|
||
|
||
04:30 PM
|
||
04:30 PM
|
||
|
||
WET
|
||
WET
|
||
|
||
|
||
|
||
INSPECTION BY ATTACHMENTS
|
||
|
||
MCDONALD-TAYLOR, H.
|
||
|
||
|
||
|
||
COMMENTS
|
||
|
||
The contract for Project Reclaim Phase II was signed on 12/28/21 and a Notice to Proceed was issued the same day.
|
||
Work at the site was already on going from Project Reclaim Phase I. Material haulage transitioned from Phase I to Phase
|
||
II on the day the contract was signed. Material haulage continues daily on the project.
|
||
|
||
Invoice #1 requested payment in the amount of $266,202.90. Payment of the invoice was recommended.
|
||
|
||
|
||
COMMONWEALTH OF VIRGINIA HNM0009561
|
||
|
||
DEPARTMENT OF MINES, MINERALS AND ENERGY
|
||
Dh DIVISION OF MINED LAND RECLAMATION
|
||
|
||
P.O. DRAWER 900, BIG STONE GAP, VA 24219
|
||
Virginia Depay TELEPHONE: (276) 523-8198
|
||
|
||
Mines Minerals and Energy
|
||
ABANDONED MINE LAND INSPECTION
|
||
|
||
PROJECT NAME, PROJECT NO, GRANT YEAR | REPORT NUMBER
|
||
Project Reclaim Phase Il 91806 2018 HNM0009561
|
||
CONTRACT INFORMATION
|
||
CONTRACT NUMBER EXPIRATION DATE, PERCENT OF CONTRACT COMPLETED
|
||
20
|
||
CONTRACTOR NAME ENGINEER NAME,
|
||
|
||
‘SITE CONTACT PERSON: Kevin Large
|
||
|
||
INSPECTION DATE, ARRIVAL DEPARTURE. GROUND CONDITION
|
||
02/03/21 03:00 PM (04:30 PM WET
|
||
02/23/21 03:30 PM 04:30 PM WET
|
||
|
||
INSPECTION BY ATTACHMENTS
|
||
|
||
MCDONALD-TAYLOR, H.
|
||
|
||
‘COMMENTS
|
||
|
||
The contract for Project Reclaim Phase Il was signed on 12/28/21 and a Notice to Proceed was issued the same day.
|
||
Work at the site was already on going from Project Reclaim Phase |. Material haulage transitioned from Phase I to Phase
|
||
Ion the day the contract was signed. Material haulage continues daily on the project.
|
||
|
||
Invoice #1 requested payment in the amount of $266,202.90. Payment of the invoice was recommended.
|
||
|
||
DMLR-AML-130S Printed: 04/06/21
|
||