COMMONWEALTH OF VIRGINIA DEPARTMENT OF MINES, MINERALS AND ENERGY

DIVISION OF MINED LAND RECLAMATION P.O. DRAWER 900, BIG STONE GAP, VA 24219

TELEPHONE: (276) 523-8198

ABANDONED MINE LAND INSPECTION

DMLR-AML-130S Printed: 04/06/21 5/06 Page 1 of 1

HNM0009561

PROJECT NAME PROJECT NO. GRANT YEAR REPORT NUMBER

Project Reclaim Phase II 91806 2018 HNM0009561

CONTRACT INFORMATION

CONTRACT NUMBER EXPIRATION DATE PERCENT OF CONTRACT COMPLETED

        20 

CONTRACTOR NAME ENGINEER NAME

SITE CONTACT PERSON: Kevin Large

INSPECTION DATE ARRIVAL DEPARTURE GROUND CONDITION

02/03/21 02/23/21

03:00 PM 03:30 PM

04:30 PM 04:30 PM

WET WET

INSPECTION BY ATTACHMENTS

MCDONALD-TAYLOR, H.

COMMENTS

The contract for Project Reclaim Phase II was signed on 12/28/21 and a Notice to Proceed was issued the same day.
Work at the site was already on going from Project Reclaim Phase I. Material haulage transitioned from Phase I to Phase II on the day the contract was signed. Material haulage continues daily on the project.

Invoice #1 requested payment in the amount of $266,202.90. Payment of the invoice was recommended.

COMMONWEALTH OF VIRGINIA HNM0009561

DEPARTMENT OF MINES, MINERALS AND ENERGY Dh DIVISION OF MINED LAND RECLAMATION

P.O. DRAWER 900, BIG STONE GAP, VA 24219 Virginia Depay TELEPHONE: (276) 523-8198

Mines Minerals and Energy ABANDONED MINE LAND INSPECTION

PROJECT NAME, PROJECT NO, GRANT YEAR | REPORT NUMBER Project Reclaim Phase Il 91806 2018 HNM0009561 CONTRACT INFORMATION CONTRACT NUMBER EXPIRATION DATE, PERCENT OF CONTRACT COMPLETED 20 CONTRACTOR NAME ENGINEER NAME,

SITE CONTACT PERSON: Kevin Large

INSPECTION DATE, ARRIVAL DEPARTURE. GROUND CONDITION 02/03/21 03:00 PM (04:30 PM WET 02/23/21 03:30 PM 04:30 PM WET

INSPECTION BY ATTACHMENTS

MCDONALD-TAYLOR, H.

COMMENTS

The contract for Project Reclaim Phase Il was signed on 12/28/21 and a Notice to Proceed was issued the same day. Work at the site was already on going from Project Reclaim Phase |. Material haulage transitioned from Phase I to Phase Ion the day the contract was signed. Material haulage continues daily on the project.

Invoice #1 requested payment in the amount of $266,202.90. Payment of the invoice was recommended.

DMLR-AML-130S Printed: 04/06/21 5/06 Page 1 of 1