nm3clol-public/Amys_Drop_Box/Golden Pond Gob Pile Project/FinalInspection_18302GoldenPonddGobRemoval/README.md
2024-06-24 05:11:34 -04:00

189 lines
2.8 KiB
Markdown

---
type: document
title: FinalInspection 18302GoldenPonddGobRemoval
file: ../FinalInspection_18302GoldenPonddGobRemoval.pdf
tags:
- Amys_Drop_Box
- Golden Pond Gob Pile Project
docDate: 2023-02-23
contentType: application/pdf
contentLength: 202907
sha256sum: c541b5165c546c133d39599688066a9f835d2b2ec6b59900d39403fe0c940fe3
sha1sum: 444d22b000e090b67317745bfe47bcce3d59dbce
---
FINAL INSPECTION
ABANDONED MINED LANDS
Golden Pond Gob Removal
Project Type: Enhanceme
nt
Grant Year: 2019 Final Inspection
Date:
2/23/2023
Construction Start Date: 2/5/2019 Construction End Date: 10/29/2021
Contract No.:
Project No.:
Location:
County:
C196013
18302
RUSSELL Contract Expiration
Date:
3/31/2023
Project Contractor: Russell County Reclamation, LLC
Contractor's
Address:
2700 Lee Highway Bristol VA 24202
Original Contract
Amount:
$0.00
Total Change Orders (CO): $0.00
Total Contract Amount: $0.00
Total Amount Invoiced:
Number of people
no longer at risk: 100
Number of people
employed: 10
Total number of change orders: 2
Page 1 of 2
DT Ty FINAL INSPECTION.
© Energy ABANDONED MINED LANDS
Golden Pond Gob Removal
Project Type: Enhanceme Grant Year: 2019 Final Inspection 2123/2023
nt Date:
Construction Start Date: 2/5/2019 Construction End Date: 10/29/2021
Contract No: 196013
Project No.: 18302
Location:
County: RUSSELL Contract Expiration 3/31/2023
Date:
Project Contractor: Russell County Reclamation, LLC
Contractor's 2700 Lee Highway Bristol VA 24202
Address:
Original Contract $0.00
Amount:
Total Change Orders (CO): $0.00 Number of people
no longer at risk: 100
Total Contract Amount: $0.00
Total Amount Invoiced: Number of people
employed 10
Total number of change orders: 2
Page 1 of 2
Features Reclaimed:
This project has been constructed in accordance with the approved engineering
plans and any applicable grant requirements (True/False) True
Comments:
Checklist:
Contractor Evaluation:
Permit(s) Requirements Complete:
Bond Release Recommended:
Retainage Release
Recommended:
Material(s) Certification(s):
Cost Breakdown Attachment Included (True/False):
NA
Y
Y
NA
NA
False
eAMLIS entry Date:
Total Cost $0.00
Problem Area Feature Reclaimed Priority Quantity Cost
0.00
GO P3 32.00 0.00
Page 2 of 2
Features Reclaimed
Problem Area Feature Reclaimed Priority Quantity Cost
0.00
Go P3 32.00 0.00
Total Cost $0.00
This project has been constructed in accordance with the approved engineering
plans and any applicable grant requirements (True/False) True
Comments:
Chee!
Contractor Evaluation: NA
Permit(s) Requirements Complete: Y
Bond Release Recommended: Y
Retainage Release NA
Recommended:
Material(s) Certification(s): NA
Cost Breakdown Attachment Included (True/False): False
eAMLIS entry Date:
Page 2 of 2