COMMONWEALTH OF VIRGINIA DEPARTMENT OF MINES, MINERALS AND ENERGY

DIVISION OF MINED LAND RECLAMATION P.O. DRAWER 900, BIG STONE GAP, VA 24219

TELEPHONE: (276) 523-8198

ABANDONED MINE LAND INSPECTION

DMLR-AML-130S Printed: 09/24/21 5/06 Page 1 of 2

HNM0009798

PROJECT NAME PROJECT NO. GRANT YEAR REPORT NUMBER

Project Reclaim Phase II 91806 2018 HNM0009798

CONTRACT INFORMATION

CONTRACT NUMBER EXPIRATION DATE PERCENT OF CONTRACT COMPLETED

        90 

CONTRACTOR NAME ENGINEER NAME

SITE CONTACT PERSON: Kevin Large

INSPECTION DATE ARRIVAL DEPARTURE GROUND CONDITION

07/13/21 07/19/21 07/27/21

03:30 PM 04:00 PM 04:00 PM

04:30 PM 04:30 PM 04:30 PM

WET WET WET

INSPECTION BY ATTACHMENTS

MCDONALD-TAYLOR, H.

COMMENTS

The contract for Project Reclaim Phase II was signed on 12/28/21 and a Notice to Proceed was issued the same day.
Work at the site was already on going from Project Reclaim Phase I. Material haulage transitioned from Phase I to Phase II on the day the contract was signed. Material haulage continues daily on the project. Removal of fines is nearly complete as well as construction of the retaining pond at the lower end of the site. Berms around the structure have been covered with a layer of topsoil.

Application for Payment #6 requested payment in the amount of $220,130.44. Payment of the invoice was recommended. Photos of the site are shown below.

COMMONWEALTH OF VIRGINIA HNM0009798 DEPARTMENT OF MINES, MINERALS AND ENERGY Dh DIVISION OF MINED LAND RECLAMATION P.O. DRAWER 900, BIG STONE GAP, VA 24219

-ginia Depai TELEPHONE: (276) 523-8198 Mines Minerals and Energy

ABANDONED MINE LAND INSPECTION

PROJECT NAME, PROJECT NO, GRANT YEAR | REPORT NUMBER Project Reclaim Phase Il 91806 2018 HNM0009798 CONTRACT INFORMATION CONTRACT NUMBER EXPIRATION DATE, PERCENT OF CONTRACT COMPLETED 90 CONTRACTOR NAME ENGINEER NAME,

SITE CONTACT PERSON: Kevin Large

INSPECTION DATE, ARRIVAL, DEPARTURE. GROUND CONDITION 07/13/21 03:30 PM (04:30 PM WET 07/19/21 04:00 PM 04:30 PM WET 07/27/24 04:00 PM 04:30 PM WET

INSPECTION BY ATTACHMENTS

MCDONALD-TAYLOR, H.

COMMENTS:

The contract for Project Reclaim Phase Il was signed on 12/28/21 and a Notice to Proceed was issued the same day. Work at the site was already on going from Project Reclaim Phase |. Material haulage transitioned from Phase | to Phase Ion the day the contract was signed. Material haulage continues daily on the project. Removal of fines is nearly complete as well as construction of the retaining pond at the lower end of the site. Berms around the structure have been covered with a layer of topsoil

Application for Payment #6 requested payment in the amount of $220,130.44. Payment of the invoice was recommended. Photos of the site are shown below.

DMLR-AML-130S Printed: 09/24/21 5/06 Page 1 of 2

COMMONWEALTH OF VIRGINIA DEPARTMENT OF MINES, MINERALS AND ENERGY

DIVISION OF MINED LAND RECLAMATION P.O. DRAWER 900, BIG STONE GAP, VA 24219

TELEPHONE: (276) 523-8198

ABANDONED MINE LAND INSPECTION

DMLR-AML-130S Printed: 09/24/21 5/06 Page 2 of 2

HNM0009798

COMMONWEALTH OF VIRGINIA

DEPARTMENT OF MINES, MINERALS AND ENERGY Dh DIVISION OF MINED LAND RECLAMATION

P.O. DRAWER 900, BIG STONE GAP, VA 24219 Virginia Depay TELEPHONE: (276) 523-8198

Mines Minerals and Energy

ABANDONED MINE LAND INSPECTION

DMLR-AML-130S 5/06 Page 2 of 2

HNM0009798

Printed: 09/24/21