COMMONWEALTH OF VIRGINIA DEPARTMENT OF MINES, MINERALS AND ENERGY
DIVISION OF MINED LAND RECLAMATION P.O. DRAWER 900, BIG STONE GAP, VA 24219
TELEPHONE: (276) 523-8198
ABANDONED MINE LAND INSPECTION
DMLR-AML-130S Printed: 02/05/21 5/06 Page 1 of 1
HNM0009482
PROJECT NAME PROJECT NO. GRANT YEAR REPORT NUMBER
Project Reclaim Phase II 91806 2018 HNM0009482
CONTRACT INFORMATION
CONTRACT NUMBER EXPIRATION DATE PERCENT OF CONTRACT COMPLETED
0
CONTRACTOR NAME ENGINEER NAME
SITE CONTACT PERSON: Kevin Large
INSPECTION DATE ARRIVAL DEPARTURE GROUND CONDITION
01/06/21 01/13/21 01/27/21
03:30 PM 03:30 PM 03:30 PM
04:30 PM 04:30 PM 04:30 PM
WET WET WET
INSPECTION BY ATTACHMENTS
MCDONALD-TAYLOR, H.
COMMENTS
The contract for Project Reclaim Phase II was signed on 12/28/21 and a Notice to Proceed was issued the same day.
Work at the site was already on going from Project Reclaim Phase I. Material haulage transitioned from Phase I to Phase
II on the day the contract was signed. Material haulage continued through the month of January and will be ongoing until
completion of the project.
COMMONWEALTH OF VIRGINIA HNMo0009482
DEPARTMENT OF MINES, MINERALS AND ENERGY Dh DIVISION OF MINED LAND RECLAMATION
P.O. DRAWER 900, BIG STONE GAP, VA 24219 Virginia Depay TELEPHONE: (276) 523-8198
Mines Minerals and Energy ABANDONED MINE LAND INSPECTION
PROJECT NAME, PROJECT NO. GRANT YEAR | REPORT NUMBER Project Reclaim Phase Il 91806 2018 HNM0009482 CONTRACT INFORMATION CONTRACT NUMBER EXPIRATION DATE, PERCENT OF CONTRACT COMPLETED 0 CONTRACTOR NAME ENGINEER NAME,
‘SITE CONTACT PERSON: Kevin Large
INSPECTION DATE, ARRIVAL DEPARTURE. GROUND CONDITION 01/06/21 03:30 PM (04:30 PM WET 01/13/21 03:30 PM 04:30 PM WET 01/27/24 03:30 PM 04:30 PM WET
INSPECTION BY ATTACHMENTS
MCDONALD-TAYLOR, H.
‘COMMENTS
The contract for Project Reclaim Phase Il was signed on 12/28/21 and a Notice to Proceed was issued the same day. Work at the site was already on going from Project Reclaim Phase |. Material haulage transitioned from Phase | to Phase Ion the day the contract was signed. Material haulage continued through the month of January and will be ongoing until ‘completion of the project.
DMLR-AML-130S Printed: 02/05/21 5106 Page 1 of 1