--- type: document title: aiHNM0009662 file: ../aiHNM0009662.pdf tags: - Amys_Drop_Box - Project Reclaim II - Final Inspection docDate: 2021-06-30 contentType: application/pdf contentLength: 318034 sha256sum: a34cb05f5d6de06d10e2e1ad5052bb9c72e0cc6decde720b3f2e71b8c93076dd sha1sum: b64dc954941fbb0711e770aa24634fc56ae41833 --- COMMONWEALTH OF VIRGINIA DEPARTMENT OF MINES, MINERALS AND ENERGY DIVISION OF MINED LAND RECLAMATION P.O. DRAWER 900, BIG STONE GAP, VA 24219 TELEPHONE: (276) 523-8198 ABANDONED MINE LAND INSPECTION DMLR-AML-130S Printed: 06/30/21 5/06 Page 1 of 2 HNM0009662 PROJECT NAME PROJECT NO. GRANT YEAR REPORT NUMBER Project Reclaim Phase II 91806 2018 HNM0009662 CONTRACT INFORMATION CONTRACT NUMBER EXPIRATION DATE PERCENT OF CONTRACT COMPLETED 20 CONTRACTOR NAME ENGINEER NAME SITE CONTACT PERSON: Kevin Large INSPECTION DATE ARRIVAL DEPARTURE GROUND CONDITION 05/11/21 05/25/21 04:00 PM 04:00 PM 04:30 PM 04:30 PM WET WET INSPECTION BY ATTACHMENTS MCDONALD-TAYLOR, H. COMMENTS The contract for Project Reclaim Phase II was signed on 12/28/21 and a Notice to Proceed was issued the same day. Work at the site was already on going from Project Reclaim Phase I. Material haulage transitioned from Phase I to Phase II on the day the contract was signed. Material haulage continues daily on the project. Work has progressed to the outer edge of the structure. Application for payment #4 requested payment in the amount of $249,764.29. Payment of the invoice was recommended. Photos of the site are shown below. COMMONWEALTH OF VIRGINIA HNMoo09662 DEPARTMENT OF MINES, MINERALS AND ENERGY Dh DIVISION OF MINED LAND RECLAMATION P.O. DRAWER 900, BIG STONE GAP, VA 24219 -ginta Depay TELEPHONE: (276) 523-8198 Mines Minerals and Energy ABANDONED MINE LAND INSPECTION PROJECT NAME PROJECT NO. GRANT YEAR [REPORT NUMBER Project Reclaim Phase Il 91806 2018 HNM0009662 CONTRACT INFORMATION CONTRACT NUMBER EXPIRATION DATE, PERCENT OF CONTRACT COMPLETED 20 CONTRACTOR NAME ENGINEER NAME ‘SITE CONTACT PERSON: Kevin Large INSPECTION DATE. ARRIVAL, DEPARTURE GROUND CONDITION 05/11/24 04:00 PM 04:30 PM ‘WET 05/25/24 04:00 PM 04:30 PM WET INSPECTION BY ATTACHMENTS MCDONALD-TAYLOR, H. ‘COMMENTS The contract for Project Reclaim Phase Il was signed on 12/28/21 and a Notice to Proceed was issued the same day. Work at the site was already on going from Project Reclaim Phase |. Material haulage transitioned from Phase | to Phase Ion the day the contract was signed. Material haulage continues daily on the project. Work has progressed to the outer edge of the structure. Application for payment #4 requested payment in the amount of $249,764.29. Payment of the invoice was recommended. Photos of the site are shown below. DMLR-AML-130S 5/06 Page 1 of 2 Printed: 06/30/21 COMMONWEALTH OF VIRGINIA DEPARTMENT OF MINES, MINERALS AND ENERGY DIVISION OF MINED LAND RECLAMATION P.O. DRAWER 900, BIG STONE GAP, VA 24219 TELEPHONE: (276) 523-8198 ABANDONED MINE LAND INSPECTION DMLR-AML-130S Printed: 06/30/21 5/06 Page 2 of 2 HNM0009662 COMMONWEALTH OF VIRGINIA HNMo0009662 DEPARTMENT OF MINES, MINERALS AND ENERGY DIVISION OF MINED LAND RECLAMATION P.O. DRAWER 900, BIG STONE GAP, VA 24219 ‘TELEPHONE: (276) 523-8198 ABANDONED MINE LAND INSPECTION " DMLR-AML-130S Printed: 06/30/21 5/06 Page 2 of 2